  1. A Texas state agency is planning a procurement for a new IT system expected to cost approximately $7 million. According to the State of Texas Procurement and Contract Management Guide, which of the following is a mandatory step in the procurement planning and formation phase for a solicitation of this value?

    Answer: Submitting the solicitation to the Contract Advisory Team (CAT) for review.

    Texas Government Code §2262.101 requires state agencies to submit solicitations with an anticipated value of $5 million or more to the Contract Advisory Team (CAT) for review and comment before issuing the solicitation. This oversight step is crucial for large contracts to ensure compliance and best value.

  2. During the needs assessment phase of procurement planning, a contract manager's primary objective is to:

    Answer: Clearly define the agency's actual requirements and objectives for the purchase.

    The needs assessment is the foundational step in procurement planning. Its purpose is to gather and document information to justify the purchase by defining the type and level of service or goods required to meet the agency's mission and objectives. This clear definition informs all subsequent steps, including market research, cost estimation, and solicitation development.

  3. Which of the following best describes the purpose of the Historically Underutilized Business (HUB) Subcontracting Plan (HSP) in the procurement formation process?

    Answer: To require prime contractors to demonstrate a good faith effort to include HUBs in subcontracting opportunities.

    The HUB program is a good faith effort program. For contracts of a certain value, prime contractors must submit a HUB Subcontracting Plan (HSP) that shows they have made a good faith effort to solicit and include certified HUBs for subcontracting opportunities. It does not guarantee awards but ensures HUBs have a fair opportunity to compete.

  4. A contract manager is preparing to procure professional services from an engineering firm. Which procurement method is required by the Professional Services Procurement Act (PSPA) in Texas?

    Answer: Request for Qualifications (RFQ), with selection based on demonstrated competence and qualifications, followed by negotiation of a fair and reasonable price.

    The Texas Professional Services Procurement Act (Texas Government Code, Chapter 2254) prohibits selecting architects, engineers, and certain other professional services based on price. The required method is to first solicit and select the most highly qualified provider based on their competence and qualifications, and only then negotiate a fair and reasonable price.

  5. When developing an acquisition plan, which of the following is a critical component that should be addressed during the procurement planning stage?

    Answer: An independent cost estimate (ICE).

    An Independent Cost Estimate (ICE) is a required and fundamental element of procurement planning. It is developed before the solicitation is issued to help the agency determine the reasonableness of offers received, budget appropriately, and assess the best value for the state.

  6. A state agency needs to purchase standard office supplies with an estimated total value of $40,000. Under Texas procurement guidelines, which of the following is the most appropriate action to take after identifying the need?

    Answer: Utilize a simplified acquisition procedure, such as soliciting quotes from multiple vendors, potentially from the Centralized Master Bidders List (CMBL).

    For purchases below the formal solicitation threshold (which is higher than $40,000), agencies can use simplified or informal procurement methods. For a purchase of this value, soliciting quotes from multiple vendors is a common and appropriate method to ensure a fair price. While formal posting to the ESBD is required for solicitations over $25,000, a full, formal IFB process may not be necessary. Using the CMBL is a best practice for finding vendors.