Software & Tools for Scheduling Flashcards

7 cards from real CST practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Software & Tools for Scheduling flashcards as text
  1. Which feature in scheduling software allows a scheduler to model multiple possible schedule scenarios without altering the live baseline?

    Answer: What-if Scenarios / Project Copies

    What-if scenario projects (or project copies) allow schedulers to test alternative plans, delays, or accelerations without affecting the approved baseline.

  2. In Microsoft Project, what happens to a task's finish date when you increase a resource's assignment units from 50% to 100%?

    Answer: The finish date moves earlier because the task completes faster

    For effort-driven tasks, doubling resource units halves the duration, causing the finish date to move earlier while total work stays constant.

  3. What is the role of an OBS (Organizational Breakdown Structure) in Primavera P6?

    Answer: Assigning responsibility for WBS elements to individuals or departments

    The OBS in P6 represents the management hierarchy and is linked to WBS nodes to assign responsibility and control access to portions of the schedule.

  4. When importing an XER file into Primavera P6, what potential conflict must the scheduler address?

    Answer: Activity IDs or project codes may already exist in the database, causing duplicates

    Duplicate Activity IDs or project numbers in the receiving P6 database can cause merge conflicts, requiring the scheduler to choose to update or add new records.

  5. Which scheduling tool capability is most critical for Integrated Master Schedule (IMS) compliance on US government contracts?

    Answer: Traceability of Work Packages to contract line items

    IMS requirements mandate that every schedule Work Package traces back to a contract Work Breakdown Structure element, ensuring full cost and schedule integration.

  6. In Primavera P6, what is the effect of enabling 'Out-of-Sequence Progress' using the 'Progress Override' option?

    Answer: The successor is allowed to continue progressing regardless of predecessor completion

    Progress Override allows successors to advance past their predecessors in the schedule, reflecting real-world out-of-sequence work without holding the logic.

  7. What does the 'Scheduling % Complete' type in Primavera P6 use to calculate an activity's earned value?

    Answer: Ratio of actual duration to planned duration

    Duration % Complete calculates progress as actual duration divided by (actual duration plus remaining duration), driving the BCWP calculation.