  1. Resource leveling in project scheduling typically results in:

    Answer: A longer project duration or changed dates

    Resource leveling resolves over-allocations by delaying activities, which often extends the project schedule.

  2. In Earned Value Management, what does BAC stand for?

    Answer: Budget at Completion

    BAC (Budget at Completion) represents the total planned budget for the entire project.

  3. A Finish-to-Finish dependency with a lag of 5 days means:

    Answer: The successor must finish 5 days after the predecessor finishes

    An FF+5 relationship means the successor activity cannot finish until 5 days after the predecessor finishes.

  4. Which estimating technique bases activity duration estimates on actual durations from similar previous projects?

    Answer: Analogous estimating

    Analogous estimating uses historical data from similar past projects as a basis for estimating current project durations.

  5. The Schedule Baseline differs from the Project Schedule in that the Schedule Baseline is:

    Answer: The approved version that can only change through formal change control

    The schedule baseline is the formally approved version of the schedule that serves as a comparison point for measuring performance.

  6. When applying the Critical Path Method, a 'near-critical path' is significant because:

    Answer: It has very little float and could become critical if delays occur

    Near-critical paths have minimal float and pose schedule risk because small delays can make them critical.

  7. In the context of project scheduling, what is a 'hammock activity'?

    Answer: A summary activity that spans between two specified activities in the network

    A hammock activity summarizes a group of related activities and its duration is determined by the start and finish of the activities it spans.