Resource leveling in project scheduling typically results in:
Answer: A longer project duration or changed dates
Resource leveling resolves over-allocations by delaying activities, which often extends the project schedule.
In Earned Value Management, what does BAC stand for?
Answer: Budget at Completion
BAC (Budget at Completion) represents the total planned budget for the entire project.
A Finish-to-Finish dependency with a lag of 5 days means:
Answer: The successor must finish 5 days after the predecessor finishes
An FF+5 relationship means the successor activity cannot finish until 5 days after the predecessor finishes.
Which estimating technique bases activity duration estimates on actual durations from similar previous projects?
Answer: Analogous estimating
Analogous estimating uses historical data from similar past projects as a basis for estimating current project durations.
The Schedule Baseline differs from the Project Schedule in that the Schedule Baseline is:
Answer: The approved version that can only change through formal change control
The schedule baseline is the formally approved version of the schedule that serves as a comparison point for measuring performance.
When applying the Critical Path Method, a 'near-critical path' is significant because:
Answer: It has very little float and could become critical if delays occur
Near-critical paths have minimal float and pose schedule risk because small delays can make them critical.
In the context of project scheduling, what is a 'hammock activity'?
Answer: A summary activity that spans between two specified activities in the network
A hammock activity summarizes a group of related activities and its duration is determined by the start and finish of the activities it spans.