Baseline & Earned Value Schedule Flashcards

7 cards from real CST practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Baseline & Earned Value Schedule flashcards as text
  1. When analyzing schedule health using EVM, a negative Schedule Variance (SV) combined with an SPI less than 1.0 most likely indicates:

    Answer: The project is behind schedule and performing less work than planned

    Both negative SV and SPI < 1.0 confirm the project is completing less work than planned, indicating a schedule delay.

  2. A project baseline change is sometimes called a 'baseline re-plan.' Under what condition is a re-plan considered inappropriate?

    Answer: When management wants to hide past schedule variances without an approved change

    Re-planning to conceal unfavorable variances without an approved change ('rubber baseline') is a misuse of the baseline process.

  3. What is the relationship between the Authorized Work (AW) and the Performance Measurement Baseline (PMB) in a government EVM system?

    Answer: AW equals PMB plus management reserve

    Total Authorized Work (AW) = PMB + Management Reserve; management reserve is held outside the PMB for unplanned scope.

  4. On a project, the actual finish date of an activity is earlier than the baseline finish date. This is referred to as:

    Answer: A baseline deviation with positive schedule variance

    When actual completion precedes the baseline date, this is a positive schedule variance or baseline deviation indicating the work finished early.

  5. Under ANSI/EIA-748 EVMS guidelines, how frequently must contractors report EVM data to the government on large contracts?

    Answer: Monthly

    ANSI/EIA-748 requires monthly reporting of cost and schedule performance data via the Contract Performance Report (CPR).

  6. What is 'undistributed budget' (UB) in the context of an EVM system?

    Answer: Authorized budget not yet assigned to a specific control account

    Undistributed Budget (UB) is authorized budget that has not yet been formally distributed to control accounts within the WBS/OBS.

  7. A project schedule baseline includes all of the following EXCEPT:

    Answer: Actual cost expenditures to date

    The schedule baseline captures planned dates, milestones, and float values, but actual costs belong to the cost baseline and financial records, not the schedule baseline.