โ† All CST Flashcard Decks

Baseline & Earned Value Schedule Flashcards

7 cards from real CST practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Baseline & Earned Value Schedule flashcards as text
  1. The Estimate to Complete (ETC) assumes all future work will be performed at the budgeted rate. Which formula represents this?

    Answer: ETC = BAC - EV

    ETC = BAC - EV assumes the remaining work will be completed at the originally planned cost efficiency (CPI = 1.0).

  2. Which of the following would NOT typically trigger a formal baseline revision?

    Answer: Weekly schedule status updates

    Weekly status updates reflect current performance against the baseline but do not themselves constitute a reason to change the baseline.

  3. On a project with BAC = $500,000, EV = $200,000, and AC = $250,000, what is the CPI?

    Answer: 0.80

    CPI = EV / AC = $200,000 / $250,000 = 0.80, meaning only 80 cents of value is being earned per dollar spent.

  4. A control account is the management control point in EVM where which two elements are integrated?

    Answer: Scope and cost against a time-phased plan

    Control accounts integrate scope and cost into a time-phased plan, enabling earned value measurement at a manageable level.

  5. What does a Variance at Completion (VAC) of -$30,000 indicate?

    Answer: The project is expected to overrun its budget by $30,000

    VAC = BAC - EAC; a negative VAC means the Estimate at Completion exceeds the Budget at Completion, projecting a cost overrun.

  6. In a time-phased budget, the cumulative Planned Value (PV) curve is commonly referred to as what shape?

    Answer: S-curve

    The cumulative PV baseline typically forms an S-curve, starting slow, accelerating through mid-project, and tapering near completion.

  7. Which earned value method assigns 50% credit at start and 50% upon completion, suitable for short-duration tasks?

    Answer: 50/50 rule

    The 50/50 rule grants 50% earned value when work begins and the remaining 50% upon task completion, useful for activities spanning one reporting period.