  1. A warehouse charges $0.08/cubic foot/month. A 10×8×6 ft shipment is stored for 3 months. What is the total fee?

    Answer: $115.20

    Volume: 480 cu ft. Monthly: $38.40. Total: $38.40 × 3 = $115.20.

  2. Workers pave 120 sq ft per hour. A road is 480 ft × 12 ft. How many hours to pave the entire section?

    Answer: 48 hours

    Area: 5,760 sq ft. Time: 5,760 ÷ 120 = 48 hours.

  3. A production line normally makes 600 units/day but runs at 75% for 4 days. How many units are produced?

    Answer: 1,800

    Reduced: 600 × 0.75 = 450/day. Over 4 days: 450 × 4 = 1,800.

  4. Equipment cost $3,600 three years ago and depreciates $400/year. What is its current value?

    Answer: $2,400

    Depreciation: 3 × $400 = $1,200. Value: $3,600 - $1,200 = $2,400.

  5. A loading dock receives: 10 small (40 lbs), 6 medium (85 lbs), 3 large (130 lbs). Total weight?

    Answer: 1,300 lbs

    Small: 400. Medium: 510. Large: 390. Total: 1,300 lbs.

  6. A job needs 8 days with 5 workers. After 3 days, 2 quit. How many more days do the 3 remaining workers need?

    Answer: 9 days

    Total: 40 worker-days. Done: 15. Remaining: 25. With 3 workers: 25 ÷ 3 ≈ 8.3 → 9 days (rounded up).