  1. A factory produces 240 units in 6 hours. At the same rate, how many units does it produce in a full 8-hour shift?

    Answer: 320

    240 ÷ 6 = 40 units/hour, and 40 × 8 = 320 units.

  2. Which number logically completes the sequence: 2, 6, 18, 54, ___?

    Answer: 162

    Each term is multiplied by 3, so 54 × 3 = 162.

  3. A manager must choose a vendor. Vendor A costs $500 with a 2-day delay; Vendor B costs $650 with same-day delivery. If a 2-day delay costs the company $200, which choice minimizes total cost?

    Answer: Vendor B ($650 effective cost)

    Vendor A's effective cost is $500 + $200 = $700, making Vendor B at $650 cheaper.

  4. If all Bloops are Razzies, and all Razzies are Lazzies, which statement must be true?

    Answer: All Bloops are Lazzies

    Since Bloops are Razzies and Razzies are Lazzies, all Bloops must be Lazzies.

  5. A project can be done in 3 sequential steps taking 4, 6, and 5 days, or split so two steps run in parallel. What is the minimum time if steps 1 and 2 run at the same time and step 3 follows?

    Answer: 11 days

    Parallel steps 1 and 2 take max(4,6)=6 days, plus step 3's 5 days equals 11 days.

  6. A store discounts a $80 item by 25%, then adds 10% sales tax. What is the final price?

    Answer: $66

    $80 × 0.75 = $60, then $60 × 1.10 = $66.

  7. Which approach best reduces the risk of a wrong decision when data is incomplete?

    Answer: Gather a few key additional facts before choosing

    Gathering key missing facts improves decision accuracy without excessive delay.

Problem Solving & Decision Making Flashcards — Wonderlic Personnel Test Study Cards with Answers