SSSTS Risk Assessment & Method Statement Review 2
What is a Method Statement and how does it relate to a risk assessment?
Select your answer
A
A Method Statement sets out the sequence of work and the safe system of work; together with the risk assessment it forms a RAMS document
B
A Method Statement is the same document as a risk assessment
C
A Method Statement replaces the risk assessment for low-risk activities
D
A Method Statement is only required for high-rise construction
Hint