  1. The Western Electric (WECO) rules are used in SPC to:

    Answer: Detect non-random patterns in control chart data

    WECO rules are a set of pattern-recognition tests applied to control charts to detect special causes beyond simple out-of-limit points.

  2. What is 'over-adjustment' (also called tampering) in the context of SPC?

    Answer: Making process adjustments in response to common cause variation

    Tampering occurs when operators make unnecessary adjustments to a process reacting to common cause variation, which actually increases overall variation.

  3. For an X-bar and R chart, after how many subgroups are the control limits considered reliable estimates?

    Answer: 20–25 subgroups

    A minimum of 20–25 subgroups is generally recommended to establish stable and reliable control limits.

  4. In a p-chart, what does the plotted statistic represent?

    Answer: The proportion of defective items in a subgroup

    The p-chart plots the proportion (fraction) of nonconforming items in each subgroup.

  5. Which measure of central tendency is plotted on the center line of a standard X-bar chart?

    Answer: The grand average of subgroup means

    The center line of an X-bar chart is the grand mean (X-double-bar), calculated as the average of all subgroup averages.

  6. A cause-and-effect (Ishikawa) diagram is most useful for:

    Answer: Brainstorming potential root causes of a quality problem

    The fishbone diagram organizes potential causes into categories (e.g., Man, Machine, Method, Material) to systematically identify root causes.

  7. What is 'sigma estimator d2' used for in SPC?

    Answer: Estimating process standard deviation from subgroup ranges

    The d2 constant is used to convert the average subgroup range (R-bar) into an unbiased estimate of the process standard deviation.