Project Planning and Management Flashcards
7 cards from real SMSTS practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Project Planning and Management flashcards as text
Under CDM 2015, who is responsible for preparing the Construction Phase Plan before work begins on site?
Answer: The Principal Contractor
The Principal Contractor must prepare the Construction Phase Plan before the construction phase begins.
A Gantt chart is primarily used in project management to:
Answer: Display task schedules and timelines visually
A Gantt chart is a bar chart that visually represents a project schedule, showing start and end dates for tasks.
What is the purpose of a 'look-ahead programme' on a construction project?
Answer: To plan work activities for the next 2–6 weeks in detail
A look-ahead programme plans near-term work in detail, typically covering the next 2–6 weeks to coordinate resources and activities.
When planning site logistics, which factor most directly affects the sequencing of construction activities?
Answer: Lead times for material delivery
Material delivery lead times can create critical constraints on when activities can start, directly affecting sequencing.
A 'critical path' in project scheduling represents:
Answer: The longest sequence of dependent tasks that determines project duration
The critical path is the longest chain of dependent activities; any delay to a task on it delays the whole project.
Which document sets out the environmental management requirements and site rules that contractors must follow?
Answer: The Site-specific Environmental Management Plan
A Site Environmental Management Plan documents site-specific controls, procedures, and responsibilities for environmental compliance.
When is it most appropriate to revise a project programme?
Answer: When unforeseen events significantly impact planned progress
Programmes should be updated when significant events such as scope changes, delays, or design changes materially affect planned activities.