Quality Control Procedures Flashcards

7 cards from real SMSTS practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Quality Control Procedures flashcards as text
  1. Under SMSTS, what is the primary purpose of a quality control inspection checklist on a construction site?

    Answer: To provide a systematic framework for verifying work meets specified standards

    Checklists provide a systematic, repeatable framework ensuring all quality criteria are consistently verified against project specifications.

  2. A sub-contractor completes formwork that deviates from the engineer's drawing tolerances. What is the FIRST action a site manager should take?

    Answer: Issue a non-conformance report and halt the pour until resolved

    A non-conformance report must be raised and work stopped to prevent embedding a defect that would be costly or impossible to rectify after concreting.

  3. Which document records all identified defects, their status, and corrective actions taken on a construction project?

    Answer: Defect register (snagging list)

    A defect register (snagging list) is the formal record tracking each defect, its resolution status, and the responsible party for correction.

  4. Concrete cube tests are taken on site primarily to:

    Answer: Verify the delivered concrete achieves the specified compressive strength

    Cube tests are crushed at 7 and 28 days to confirm the concrete batch meets the design compressive strength before loading the structure.

  5. What does 'hold point' mean in a quality inspection plan (ITP)?

    Answer: A stage at which work must stop until an authorized inspection is completed and approved

    A hold point requires work to halt and a designated authority to inspect and sign off before any further construction activity proceeds.

  6. Which British Standard governs the specification for concrete production and conformity?

    Answer: BS EN 206

    BS EN 206 specifies requirements for concrete production, including constituent materials, properties, and conformity criteria.

  7. On an SMSTS-managed site, who is ultimately responsible for ensuring quality control procedures are implemented?

    Answer: The site manager

    The site manager holds ultimate responsibility for implementing and enforcing the project's quality control procedures on a day-to-day basis.