Practical Application in Site Management Flashcards

7 cards from real SMSTS practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Practical Application in Site Management flashcards as text
  1. What does 'permit to work' system achieve on a construction site?

    Answer: It provides a formal control system ensuring hazardous tasks are properly authorised and managed

    A permit to work is a formal documented system that authorises and controls non-routine, high-risk work activities.

  2. Silica dust is identified during cutting of block paving. Which control measure best reduces inhalation risk at source?

    Answer: Use wet cutting methods or on-tool extraction to suppress dust at source

    Wet cutting or on-tool dust extraction controls silica dust at source, which is more effective than relying solely on RPE.

  3. A crane lift plan is being reviewed. Which factor is MOST critical to verify before a lift proceeds?

    Answer: The safe working load of the crane relative to the load weight, radius, and ground conditions

    The safe working load must never be exceeded, and capacity is directly affected by load weight, operating radius, and ground bearing capacity.

  4. Under CDM 2015, when must the Health and Safety File be handed to the client?

    Answer: At the end of the construction phase upon project completion

    The principal designer must hand the completed Health and Safety File to the client at project completion for future maintenance and refurbishment use.

  5. Workers complain of heat stress symptoms during a summer heatwave on site. What is the FIRST management action?

    Answer: Move affected workers to a cool area, provide water, and monitor their condition

    Heat stroke is life-threatening; immediate cooling, hydration, and monitoring are the first priority before escalating to medical help if needed.

  6. Which sign shape and colour indicates a mandatory action on a construction site?

    Answer: Blue circle with a white symbol

    Blue circular signs indicate mandatory requirements, such as 'hard hat must be worn', as defined by BS EN ISO 7010.

  7. A site manager must demonstrate continual improvement in health and safety performance. Which metric is the BEST leading indicator?

    Answer: Number of near-miss reports submitted by workers

    Near-miss reporting is a leading indicator that reveals hazards before they cause harm, unlike accident data which is reactive.