  1. Who is legally responsible for ensuring the Construction Phase Plan is prepared before construction work begins?

    Answer: The principal contractor

    Under CDM 2015, the principal contractor has a legal duty to prepare the Construction Phase Plan before construction work begins.

  2. What must be recorded in a scaffold inspection report?

    Answer: Date of inspection, condition of scaffold, any defects found, and inspector's name

    A scaffold inspection report must document the date, inspector's identity, condition, defects found, and remedial action required.

  3. In the context of site documentation, what is a 'safe system of work'?

    Answer: A documented procedure describing how to perform a task safely

    A safe system of work is a formal procedure that integrates hazard identification and control measures into step-by-step work instructions.

  4. How frequently must scaffolding be formally inspected under the Work at Height Regulations 2005?

    Answer: Every 7 days and after any event likely to affect stability

    Scaffolding must be inspected at least every 7 days and after any event such as severe weather that could affect its structural integrity.

  5. What is the key difference between a method statement and a risk assessment?

    Answer: A risk assessment identifies hazards and controls; a method statement describes how work will be done safely

    A risk assessment identifies hazards and evaluates risk levels, while a method statement describes the safe sequence of work steps incorporating those controls.

  6. When an employee reports an unsafe condition to a site manager, what is the most appropriate immediate documentation step?

    Answer: Record it in the site safety observation log and investigate promptly

    Unsafe conditions should be recorded in a site safety observation log and investigated immediately to prevent incidents.

  7. Which document establishes the pre-construction information that the principal designer must provide?

    Answer: The pre-construction information pack

    The pre-construction information pack is prepared by the principal designer and contains existing health and safety information relevant to the project.