  1. After mechanical completion of a PV plant, which activity verifies that the system performs as designed before the owner accepts it?

    Answer: Commissioning and performance testing

    Commissioning includes functional tests and a capacity or performance ratio test to confirm design output before acceptance.

  2. A solar project manager identifies a risk that module tariffs may increase costs and buys insurance against it. Which risk response strategy is this?

    Answer: Transfer

    Transferring risk shifts its financial impact to a third party such as an insurer or supplier.

  3. Which surety instrument guarantees that the EPC contractor will complete the solar project according to contract terms?

    Answer: Performance bond

    A performance bond protects the owner if the contractor fails to complete the work as specified.

  4. A solar project has BAC = $10M, EV = $4M, and AC = $5M. What is the cost variance (CV)?

    Answer: -$1M

    CV = EV − AC = $4M − $5M = −$1M, meaning the project is over budget.

  5. What is the main purpose of the submittal process during solar construction?

    Answer: To let the engineer review and approve equipment and materials before installation

    Submittals let the engineer of record confirm proposed products such as inverters and racking meet the specifications.

  6. Adding a second pile-driving crew to shorten a critical-path activity at extra cost is called:

    Answer: Crashing

    Crashing adds resources to critical-path activities to reduce duration at the lowest additional cost.

  7. Why is an ALTA/NSPS land title survey typically required early in utility-scale solar development?

    Answer: To define boundaries, easements, and encumbrances for financing and title insurance