โ† All PMP Flashcard Decks

Managing Budget and Costs Flashcards

7 cards from real PMP practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Managing Budget and Costs flashcards as text
  1. A project has a BAC of $500,000, EV of $200,000, and AC of $250,000. What is the Cost Performance Index (CPI)?

    Answer: 0.80

    CPI = EV / AC = $200,000 / $250,000 = 0.80, meaning only $0.80 of value is earned for every $1 spent.

  2. Which cost estimation technique uses statistical relationships between historical data and project variables to calculate cost estimates?

    Answer: Parametric estimating

    Parametric estimating uses statistical relationships (e.g., cost per unit) derived from historical data to calculate estimates.

  3. A project manager notices the CPI has been consistently 0.75 for the past three months. What is the most likely Estimate at Completion (EAC)?

    Answer: EAC = BAC / CPI

    When the CPI is expected to remain the same, EAC = BAC / CPI is the most appropriate formula.

  4. What does a negative Cost Variance (CV) indicate about a project?

    Answer: The project is over budget

    A negative CV (EV - AC < 0) means actual costs exceed earned value, indicating the project is over budget.

  5. A project manager is asked to provide a rough order of magnitude (ROM) estimate. What is the typical accuracy range for a ROM estimate?

    Answer: -25% to +75%

    ROM estimates are typically accurate within -25% to +75% and are used in the early phases of a project.

  6. Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?

    Answer: Control Costs

    Control Costs is the process of monitoring project status to update costs and managing changes to the cost baseline.

  7. A project has EV = $300,000, PV = $350,000, and AC = $280,000. Which statement is correct?

    Answer: The project is under budget but behind schedule

    CV = EV - AC = $20,000 (positive = under budget); SV = EV - PV = -$50,000 (negative = behind schedule).