Resource Leveling & Optimization Flashcards

7 cards from real PMI-SP practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Resource Leveling & Optimization flashcards as text
  1. Resource leveling is primarily used to resolve which type of scheduling conflict?

    Answer: Over-allocation of resources beyond availability limits

    Resource leveling addresses over-allocation by adjusting activity start and finish dates so no resource is assigned beyond its maximum availability.

  2. Which of the following is the most significant consequence of applying resource leveling to a schedule?

    Answer: The project end date may be extended beyond the original baseline

    Resource leveling often extends the project end date because activities must be delayed to resolve resource over-allocations.

  3. In PMI scheduling terminology, what distinguishes resource leveling from resource smoothing?

    Answer: Resource smoothing maintains project end date; resource leveling may extend it

    Resource smoothing adjusts activities only within available float and does not extend the project end date, while resource leveling may push the end date.

  4. A scheduler notices that a senior engineer is assigned 14 hours of work on a single day with an 8-hour availability. What is the BEST first step?

    Answer: Analyze float on conflicting activities before deciding to level or smooth

    Before applying leveling or smoothing, the scheduler should evaluate available float to determine which technique best resolves the conflict without unnecessary schedule impact.

  5. Which scheduling technique delays non-critical activities within their float to reduce peak resource demand without changing the project end date?

    Answer: Resource smoothing

    Resource smoothing uses available float on non-critical activities to redistribute resource demand while preserving the project end date.

  6. When performing resource leveling, which priority rule assigns resource availability first to the activity with the least total float?

    Answer: Minimum float priority (least float first)

    The minimum float (least float first) heuristic prioritizes activities closest to becoming critical, preserving schedule flexibility for less constrained activities.

  7. A project schedule shows a resource histogram with a spike of 150% utilization for two days. The scheduler decides to split an activity to resolve this. What must the scheduler verify after splitting?

    Answer: That the split does not create a new critical path or violate logic constraints

    Splitting an activity can inadvertently create new critical paths or conflict with existing schedule logic, so the scheduler must validate the network after any split.