Earned Value Management (EVM) Flashcards
7 cards from real PMBOK practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Earned Value Management (EVM) flashcards as text
A project has a BAC of $500,000, EV of $200,000, and AC of $250,000. What is the Cost Performance Index (CPI)?
Answer: 0.80
CPI = EV / AC = $200,000 / $250,000 = 0.80, meaning the project is getting $0.80 of value for every $1 spent.
Which EVM metric best indicates whether a project will finish on time?
Answer: Schedule Performance Index (SPI)
SPI = EV / PV and measures schedule efficiency; an SPI below 1.0 indicates the project is behind schedule.
The To-Complete Performance Index (TCPI) based on BAC is calculated as:
Answer: (BAC - EV) / (BAC - AC)
TCPI (BAC) = (BAC - EV) / (BAC - AC), representing the cost efficiency needed on remaining work to meet the original budget.
A project's SPI is 1.2 and CPI is 0.9. How should the project manager interpret this?
Answer: Ahead of schedule but over budget
SPI > 1.0 means ahead of schedule; CPI < 1.0 means over budget — a combination requiring cost control attention.
Estimate at Completion (EAC) using the formula EAC = AC + (BAC - EV) assumes:
Answer: The remaining work will be done at the budgeted rate
EAC = AC + (BAC - EV) assumes the remaining work will be completed exactly as originally planned (at budget).
Which of the following represents Variance at Completion (VAC)?
Answer: BAC - EAC
VAC = BAC - EAC; a negative VAC indicates the project is expected to finish over budget.
On a project with PV = $300,000, EV = $270,000, and AC = $260,000, what is the Schedule Variance (SV)?
Answer: -$30,000
SV = EV - PV = $270,000 - $300,000 = -$30,000, indicating the project is behind schedule by $30,000 in value.