PMBOK - Project Management Body of Knowledge Practice Test
PMBOK PMBOK Risk Management Processes Questions and Answers 3
What distinguishes a residual risk from a secondary risk?
Select your answer
A
Residual risks remain after responses are implemented; secondary risks arise as a direct result of implementing a response
B
Residual risks are always high priority; secondary risks are always low priority
C
Residual risks occur only during execution; secondary risks occur during planning
D
There is no meaningful distinction between the two
Hint