What does the Schedule Performance Index (SPI) measure in project schedule tracking?
Select your answer
A
The ratio of budgeted cost of work performed to actual cost
B
The ratio of earned value to planned value
C
The ratio of planned value to actual cost
D
The ratio of budget at completion to estimate at completion