PMBOK - Project Management Body of Knowledge Practice Test
PMBOK PMBOK Project Cost Management Questions and Answers 3
What is a Control Account in PMBOK cost management?
Select your answer
A
A bank account used to manage project disbursements
B
A management control point where scope, budget, and schedule are integrated and measured
C
An account tracking only actual project expenditures
D
A reserve fund for handling cost overruns
Hint