NCMA - National Contract Management Association Certification NCMA - National Contract Management Association Contract Modifications and Closeout Questions and Answers
A contracting officer issues a written order to the contractor that changes the specification of a component. This change is within the general scope of the contract. The contractor believes this change will increase their cost and performance time. According to the Federal Acquisition Regulation (FAR), what type of modification is this initially, and what is required for the contractor to receive an equitable adjustment?