NABCEP Cheat Sheet 2026

The 30 highest-yield NABCEP facts, distilled from real exam questions. Print it, save it as a PDF, or study it here — free, no sign-up.

70 questions
240 min time limit
70.00% to pass
  1. What is the primary consideration when selecting the orientation of PV modules in the Northern Hemisphere? South
  2. What document does a utility typically require before allowing a customer-owned small wind system to connect to the grid? An executed interconnection agreement
  3. What is the minimum required clearance around battery energy storage systems for maintenance access per NFPA 855? 36 inches on service side, per equipment labeling and local AHJ requirements
  4. Which document should a commissioning technician provide to the system owner at project closeout? As-built drawings, system manual, and commissioning report
  5. What is the primary hazard when performing maintenance on a PV array that cannot be fully de-energized by shutting off the inverter? PV modules continue to produce DC voltage in daylight even with the inverter off
  6. What is the typical depth of discharge (DoD) limit recommended to maximize cycle life in lithium-ion battery storage systems? 80–90% DoD as the operational maximum
  7. An inspector finds that PV module mounting hardware is not listed for the specific roof type (e.g., tile roof). What action is appropriate? Fail the inspection and require listed hardware appropriate for the roof type
  8. Which heat transfer fluid is commonly used in closed-loop solar thermal systems to prevent freezing? Propylene glycol-water mixture
  9. What type of generator is most commonly used in small wind turbines? Permanent magnet alternator
  10. Which IEC standard governs the design requirements and safety of wind turbines used in small wind energy system applications? IEC 61400-2 (Design requirements for small wind turbines)
  11. What is the Rayleigh distribution used for in small wind site assessment? Modeling the statistical frequency of wind speeds at a site
  12. What interval is typically recommended for a full preventive maintenance inspection of a commercial grid-tied PV system? Annually, at minimum
  13. How does temperature affect the performance of PV modules? Higher temperatures decrease module efficiency
  14. What is the typical warranty cycle life for a quality residential lithium-ion battery storage system? 4,000–6,000 cycles or more
  15. Which NEC article specifically governs the installation of small wind electric systems? Article 694
  16. Which NEC article specifically addresses energy storage systems (ESS) including battery installations? NEC Article 480
  17. What is the purpose of a shading analysis during the design phase of a PV system? To identify potential obstructions that could reduce system performance
  18. When sizing a battery storage system for self-consumption optimization, what load data is most critical? Historical hourly load profile of the facility
  19. A combiner box fuse blows repeatedly in the same string position. What is the most appropriate next step? Inspect the string for a ground fault or short circuit
  20. Which battery chemistry is currently most common in utility-scale and residential energy storage systems in the US? Lithium iron phosphate (LFP) and other lithium-ion chemistries
  21. At what reference wind speed are small wind turbines typically rated for power output per IEC 61400-2 and AWEA standards? 24.6 mph (11 m/s)
  22. Which federal agency must be notified for wind turbine installations that exceed certain heights near airports or in navigable airspace? FAA (Federal Aviation Administration)
  23. What does 'wind rose' data tell a site assessor? The frequency and speed distribution of wind from each compass direction at a site
  24. What maintenance task should be performed on PV module surfaces in dusty or arid climates more frequently than in other regions? Cleaning to remove soiling
  25. When performing a site assessment, why is it important to consider shading analysis? To identify potential obstacles that could reduce system performance
  26. What document establishes the maximum allowable energy capacity of battery energy storage systems installed in residential occupancies? NFPA 855 Standard for the Installation of Stationary Energy Storage Systems
  27. During maintenance, you discover arc marks inside an outdoor DC combiner box. What should you do first? De-energize the affected circuits and identify the cause before restoring power
  28. Why is it important to consider local building codes and regulations when designing a PV system? To avoid penalties and ensure the safety and compliance of the installation
  29. What grounding requirement applies to metal towers used for small wind turbines? Towers must be connected to the system equipment grounding conductor
  30. What is the primary purpose of a commissioning inspection for a newly installed PV system? To verify the system operates safely and as designed before handover