โ† All IN BAR Flashcard Decks

Contracts and Sales Flashcards

7 cards from real IN BAR practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Contracts and Sales flashcards as text
  1. A 17-year-old buys a car, continues driving it after turning 18, and makes two payments as an adult. The contract is most likely:

    Answer: Enforceable, because continued use and payment after majority ratifies it

    A minor's contract is voidable, but conduct affirming the contract after reaching majority constitutes ratification.

  2. A general contractor uses a subcontractor's bid to compute its own winning bid, and the sub then tries to revoke. The sub's bid is most likely:

    Answer: Irrevocable under promissory estoppel because reliance was foreseeable and actual

    Under Drennan-style promissory estoppel, a sub's bid is held open when the general foreseeably and reasonably relies on it in submitting its own bid.

  3. Goods are destroyed in transit under a shipment contract (FOB seller's city) after the seller duly delivered them to the carrier. Who bears the risk of loss?

    Answer: The buyer, because risk passed on delivery to the carrier

    In a shipment contract, risk of loss passes to the buyer when the goods are duly delivered to the carrier.

  4. An employer threatens to fire an at-will employee unless she signs a release of valid legal claims, leaving her no reasonable alternative. The release is most vulnerable to attack on grounds of:

    Answer: Economic duress

    A wrongful threat that leaves the victim no reasonable alternative supports rescission for economic duress.

  5. A seller delivers goods and the buyer uses them for two months before complaining of obvious defects. Under UCC 2-606 and 2-602, the buyer has most likely:

    Answer: Accepted the goods by failing to make an effective rejection within a reasonable time

    Acceptance occurs when the buyer fails to reject within a reasonable time after an opportunity to inspect, or acts inconsistently with the seller's ownership.

  6. A liquidated damages clause in a construction contract fixes damages at $1,000 per day of delay. The clause is enforceable if:

    Answer: Damages were difficult to estimate at formation and the amount is a reasonable forecast

    Liquidated damages are valid when actual damages were hard to estimate at contracting and the sum is a reasonable forecast rather than a penalty.

  7. A debtor honestly disputes the amount owed and sends a check marked 'payment in full' for a lesser sum, which the creditor cashes. The debt is most likely:

    Answer: Discharged by accord and satisfaction because the claim was subject to a good-faith dispute

    Cashing a full-payment check tendered in good faith on a genuinely disputed claim effects an accord and satisfaction.