A construction company is performing a risk assessment for a new high-rise building project.
The safety team uses a risk matrix to evaluate identified hazards.
One specific hazard, 'working at height', is assigned a high probability of occurrence and a catastrophic severity.
In a standard risk matrix, what is the MOST appropriate next step?