An agile team has completed three two-week sprints.
The story points completed for each sprint were 18, 24, and 21 respectively.
A crucial user story in the current sprint was only partially completed.
The total estimated points for the current sprint's completed stories is 20, and the partially completed story is estimated at 8 points.
What is the team's velocity that should be used for planning the next sprint?