  1. Which type of dependency between tasks means Task B cannot start until Task A finishes?

    Answer: Finish-to-Start (FS)

    A Finish-to-Start dependency means the predecessor task must complete before the successor task can begin.

  2. An engineering technician is asked to perform a 'punch list' walk-through. What project phase does this typically occur in?

    Answer: Project closeout

    A punch list identifies remaining deficiencies or incomplete items during project closeout before final acceptance.

  3. What does a RACI matrix define in a project?

    Answer: Roles and responsibilities for project tasks

    A RACI matrix defines who is Responsible, Accountable, Consulted, and Informed for each task or decision in a project.

  4. Which document establishes the approved version of the project schedule used as a reference for measuring performance?

    Answer: Schedule baseline

    The schedule baseline is the approved version of the project schedule against which actual performance is measured.

  5. What does 'lag' mean in the context of project scheduling?

    Answer: A delay added between the end of one task and start of the next

    Lag is a waiting period between the end of a predecessor task and the start of a successor task, causing a deliberate delay.

  6. In engineering project documentation, which report format provides a brief snapshot of project status including scope, schedule, cost, and risk?

    Answer: Status report

    A status report summarizes the current state of the project across key performance areas for stakeholder communication.

  7. What is the purpose of configuration management in engineering projects?

    Answer: To control changes to project deliverables and maintain documentation integrity

    Configuration management ensures that changes to project deliverables are systematically tracked and controlled to maintain integrity.

Project Management & Documentation Flashcards โ€” ETC Study Cards with Answers