What is DBIA's recommended approach to risk allocation in design-build contracts?
Select your answer
A
Transfer all risk to the design-builder
B
Allocate each risk to the party best able to manage, mitigate, or absorb that risk
C
The owner should retain all project risk
D
Risk allocation should not be discussed until problems arise