Technology Project Management Flashcards
7 cards from real CTE practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Technology Project Management flashcards as text
Which document formally authorizes a telecom project and grants the project manager authority to apply resources?
Answer: Project charter
The project charter formally initiates the project and gives the project manager organizational authority to proceed.
A PM calculates that the Estimate at Completion (EAC) for a network expansion is $2.4M vs. the original Budget at Completion (BAC) of $2.0M. What does this indicate?
Answer: The project is forecasted to overrun by $400K
When EAC exceeds BAC, the project is projected to cost more than originally budgeted — here by $400K.
In the context of telecom projects, what is a 'cutover' plan primarily concerned with?
Answer: Transitioning from old to new systems with minimal service disruption
A cutover plan details the steps, timing, and rollback procedures for switching from legacy to new systems while minimizing downtime.
Which scheduling technique identifies all possible paths through a project network and determines the longest one?
Answer: Critical Path Method (CPM)
CPM maps all task sequences and finds the longest path (critical path), which determines the minimum project duration.
A telecom project manager is using Monte Carlo simulation during risk analysis. What is the primary output of this technique?
Answer: A probability distribution of possible project outcomes
Monte Carlo simulation runs thousands of scenarios using variable inputs to produce a probability distribution of schedule and cost outcomes.
Which change management process ensures only approved changes are incorporated into a telecom project baseline?
Answer: Integrated change control
Integrated change control reviews, approves, or rejects all change requests to protect the project baselines.
What is the key difference between a project and a program in telecommunications management?
Answer: A program is a group of related projects managed in a coordinated way
A program groups related projects to obtain benefits and control not available when managing them individually.