A CSM is building a staffing management plan. Which input is MOST critical for determining when each role needs to be on the project?
Answer: Project schedule and activity resource requirements
The project schedule and activity resource requirements directly dictate when specific skills are needed, forming the foundation of the staffing plan.
A project team consistently misses sprint commitments because developers are pulled into production support. This is best addressed by:
Answer: Formally allocating a defined percentage of capacity to support in sprint planning
Explicitly reserving capacity for known interruptions like support during sprint planning gives the team a realistic, achievable commitment.
Which network diagram dependency type states that a successor cannot finish until its predecessor finishes?
Answer: Finish-to-Finish (FF)
Finish-to-Finish means the successor task cannot complete until the predecessor task has also completed.
A software project has a Schedule Performance Index (SPI) of 1.2. What does this indicate?
Answer: The project is progressing 20% faster than planned
SPI = EV / PV; an SPI greater than 1.0 means more work is being accomplished than planned, indicating the project is ahead of schedule.
In resource planning, a histogram showing resource demand versus availability over time is called a:
Answer: Resource histogram
A resource histogram visually displays resource demand versus capacity over time, making over-allocation and under-utilization immediately apparent.
Which technique involves breaking project scope into smaller, more manageable components to improve cost and schedule estimates?
Answer: Work breakdown structure (WBS) decomposition
WBS decomposition breaks deliverables into work packages, enabling more accurate bottom-up estimation of cost, duration, and resource needs.
A CSM must choose between two resource allocation approaches for a new feature: assigning a specialist who will be 100% utilized versus three generalists at 33% each. The MAIN advantage of the specialist approach is:
Answer: Reduced coordination overhead and faster task completion
A dedicated specialist minimizes context-switching and coordination overhead, typically resulting in faster, higher-quality output on focused tasks.