Submittals & Shop Drawings Flashcards

7 cards from real CSI practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Submittals & Shop Drawings flashcards as text
  1. Which CSI publication provides the most comprehensive guidance on organizing and managing the submittal process?

    Answer: Project Delivery Practice Guide

    The CSI Project Delivery Practice Guide addresses submittal procedures, responsibilities, and best practices in depth within its construction administration sections.

  2. A specification requires 'certified test reports' for a roofing membrane. Who typically certifies these reports?

    Answer: The manufacturer or an independent testing laboratory

    Certified test reports are prepared by the material manufacturer or an accredited independent laboratory that conducted and documented the performance testing.

  3. What is the primary reason shop drawings for curtain wall systems often require a licensed engineer's seal?

    Answer: The contractor's engineer takes responsibility for the structural and water-infiltration performance design

    Curtain wall systems involve delegated design, where the contractor's structural engineer of record takes design responsibility and seals drawings to confirm engineering adequacy.

  4. Which element must appear on every sheet of a shop drawing set to ensure traceability back to the contract documents?

    Answer: The specification section number to which the drawing relates

    Referencing the applicable specification section number on shop drawings ties fabrication details back to the contractual requirements they are meant to fulfill.

  5. When a mock-up is required by the specifications, what submittal documentation typically accompanies the mock-up review?

    Answer: Product data, samples, and sometimes shop drawings used to construct the mock-up

    Mock-up reviews are supported by the same submittals used for the actual work—product data, samples, and shop drawings—so reviewers can evaluate real materials and methods.

  6. A subcontractor submits shop drawings directly to the architect without routing through the general contractor. What is the standard industry response?

    Answer: The architect should return them unreviewed and require resubmission through the general contractor

    Standard practice requires all submittals to flow through the general contractor, who must review and stamp them before forwarding, maintaining the single point of responsibility.

  7. What does 'close-out submittal' refer to in CSI construction administration terminology?

    Answer: Final submittals such as operation manuals, warranties, and as-built drawings delivered at project completion

    Close-out submittals are the final project record documents—including O&M manuals, warranties, attic stock lists, and as-built drawings—required before final completion is certified.