AIA Contract Documents Flashcards
7 cards from real CSI practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 AIA Contract Documents flashcards as text
Which AIA document establishes the legal relationship between a Contractor and Subcontractor?
Answer: A401
AIA A401 is the Standard Form of Agreement Between Contractor and Subcontractor.
Under AIA A201-2017, the term 'Substantial Completion' is defined as the stage when:
Answer: The Work is sufficiently complete for the Owner to occupy or use it for its intended purpose
A201 §9.8.1 defines Substantial Completion as when the Work is sufficiently complete so the Owner can occupy or utilize it for its intended purpose.
The AIA C401 document governs the relationship between which parties?
Answer: Architect and Consultant
AIA C401 is the Standard Form of Agreement Between Architect and Consultant, used for engineering or specialty subconsultants.
In AIA A201-2017, a Construction Change Directive (CCD) is used when:
Answer: The Owner and Contractor cannot agree on the cost or time adjustment but work must proceed
A CCD under §7.3 allows the Owner and Architect to direct changes when agreement on cost or time cannot be reached but work must proceed immediately.
Which AIA document is specifically tailored for Sustainable Projects incorporating LEED or similar rating systems?
Answer: AIA E204
AIA E204 is the Sustainable Projects Exhibit, used as an attachment to other agreements to address sustainable design and construction responsibilities.
The AIA Document G702 is the standard form for:
Answer: Application and Certificate for Payment
G702 is the Application and Certificate for Payment form used by the Contractor to request and the Architect to certify progress payments.
Under AIA A201-2017, who bears the cost of testing and inspection if a test reveals the Work does NOT conform to Contract requirements?
Answer: The Contractor
A201 §13.4 states that if testing reveals non-conforming Work, the Contractor bears the cost of the test and any necessary correction.