Environmental Awareness Flashcards

6 cards from real CSCS practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 6 Environmental Awareness flashcards as text
  1. What is a Site Waste Management Plan (SWMP) and what is its purpose on a construction project?

    Answer: A SWMP is a document that forecasts the types and quantities of waste a construction project will produce, sets targets for waste minimisation, and records how waste is actually managed throughout the project lifecycle

    Although the mandatory SWMP Regulations 2008 were revoked in 2013, SWMPs remain best practice and are often required by clients, planning conditions, and BREEAM assessments. A SWMP forecasts waste types and volumes, identifies opportunities for waste prevention and reuse, sets recycling targets, and provides an ongoing record of waste management decisions throughout the project.

  2. What legal protection do bats receive on UK construction sites?

    Answer: All bat species and their roosts are protected under the Wildlife and Countryside Act 1981 and the Conservation of Habitats and Species Regulations 2017 — it is an offence to deliberately kill, injure, capture, or disturb bats or damage/destroy their roosts

    All 18 UK bat species are European Protected Species. Under the Wildlife and Countryside Act 1981 and the Conservation of Habitats and Species Regulations 2017, it is a criminal offence to deliberately capture, injure, or kill a bat; deliberately disturb bats; or damage or destroy a bat roost (even when unoccupied). Construction work affecting bats requires a licence from Natural England, and ecological surveys must be conducted before demolition or renovation.

  3. What is the legal requirement for dealing with contaminated land discovered during construction work?

    Answer: Contaminated land must be reported to the local authority and/or Environment Agency, and contaminated soils must be tested, classified, and disposed of at appropriately licensed facilities — work in affected areas may need to stop until a remediation strategy is agreed

    Under Part 2A of the Environmental Protection Act 1990, contaminated land must be identified, assessed, and remediated. If contamination is discovered during construction, the local authority and/or Environment Agency must be notified. Contaminated soils must be tested, classified as hazardous or non-hazardous waste, and disposed of at appropriately permitted facilities. A remediation strategy must be agreed before construction continues.

  4. What measures must be taken to prevent pollution of watercourses from a construction site?

    Answer: Silt fences, settlement ponds, bunded fuel storage, spill kits, and sustainable drainage must be used to prevent sediment, oil, chemicals, and cement washings from entering any watercourse or drain — it is an offence under the Environmental Permitting Regulations 2016 to cause or knowingly permit a water discharge activity without a permit

    Under the Environmental Permitting (England and Wales) Regulations 2016, it is an offence to cause or knowingly permit a water discharge activity (pollution of a watercourse) without a permit. Construction sites must implement pollution prevention measures including silt fences, settlement ponds, bunded storage, spill kits, designated washout areas for concrete, and protection of drains. The Environment Agency can prosecute and impose unlimited fines.

  5. What is the legal status of great crested newts in relation to UK construction projects?

    Answer: Great crested newts are a European Protected Species — it is an offence to kill, injure, capture, or disturb them, or to damage or destroy their breeding sites and resting places, requiring an ecological survey and possible mitigation licence before construction

    Great crested newts are protected under the Wildlife and Countryside Act 1981 and the Conservation of Habitats and Species Regulations 2017. It is a criminal offence to deliberately kill, injure, or capture them; disturb them in a way that affects their ability to survive or breed; or damage/destroy their breeding or resting places. Construction projects within 500m of known populations require ecological surveys and may need a European Protected Species mitigation licence from Natural England.

  6. What are the requirements for segregating construction waste on site?

    Answer: Construction waste should be segregated into separate containers for different waste streams (wood, metal, plasterboard, plastics, inert waste, hazardous waste) to maximise recycling and comply with the waste hierarchy requirements of the Waste Regulations 2011

    The Waste (England and Wales) Regulations 2011 require the application of the waste hierarchy, which is best achieved through on-site segregation. Separating waste into streams (timber, metals, plasterboard, plastics, inert materials, and hazardous wastes) maximises recycling rates and reduces landfill disposal. Mixed waste is more expensive to dispose of and harder to recycle. Some materials (e.g., plasterboard) must not be co-disposed with biodegradable waste.