Which contract type places the greatest financial risk on the contractor if costs exceed estimates?
Answer: Lump sum (fixed price)
Under a lump sum contract the contractor bears all cost overrun risk since the price is fixed regardless of actual costs.
What is the purpose of a pre-construction meeting with subcontractors?
Answer: To align all parties on schedule, site rules, and communication procedures
Pre-construction meetings establish expectations for schedule, safety, coordination, and communication before work begins.
Which scheduling constraint requires a successor activity to start no earlier than a specified date, regardless of predecessor completion?
Answer: Start-no-earlier-than (SNET)
A Start-No-Earlier-Than constraint forces the activity to wait until a defined calendar date before it can begin.
When scheduling inspections, a contractor should order them so that:
Answer: Each inspection is scheduled only after the preceding required inspection is passed
Building codes require inspections in sequence; work cannot be covered until the relevant inspection is approved.
A 'look-ahead schedule' in residential construction typically covers what time horizon?
Answer: Two to six weeks
Look-ahead schedules (typically 2–6 weeks) provide short-term planning detail to coordinate crews and materials in the near term.
Which WBS (Work Breakdown Structure) level directly relates to cost account tracking in residential construction?
Answer: Level 3 — work package
Work packages at Level 3 of the WBS are the lowest level where cost and schedule are assigned and tracked.
A subcontractor's work depends on the general contractor supplying temporary power. This is best documented as:
Answer: A constraint or assumption in the schedule
Owner- or GC-furnished items that a subcontractor depends on must be documented as constraints or assumptions so accountability is clear.