Project Planning & Scheduling Flashcards

7 cards from real CRC practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Project Planning & Scheduling flashcards as text
  1. Which contract type places the greatest financial risk on the contractor if costs exceed estimates?

    Answer: Lump sum (fixed price)

    Under a lump sum contract the contractor bears all cost overrun risk since the price is fixed regardless of actual costs.

  2. What is the purpose of a pre-construction meeting with subcontractors?

    Answer: To align all parties on schedule, site rules, and communication procedures

    Pre-construction meetings establish expectations for schedule, safety, coordination, and communication before work begins.

  3. Which scheduling constraint requires a successor activity to start no earlier than a specified date, regardless of predecessor completion?

    Answer: Start-no-earlier-than (SNET)

    A Start-No-Earlier-Than constraint forces the activity to wait until a defined calendar date before it can begin.

  4. When scheduling inspections, a contractor should order them so that:

    Answer: Each inspection is scheduled only after the preceding required inspection is passed

    Building codes require inspections in sequence; work cannot be covered until the relevant inspection is approved.

  5. A 'look-ahead schedule' in residential construction typically covers what time horizon?

    Answer: Two to six weeks

    Look-ahead schedules (typically 2–6 weeks) provide short-term planning detail to coordinate crews and materials in the near term.

  6. Which WBS (Work Breakdown Structure) level directly relates to cost account tracking in residential construction?

    Answer: Level 3 — work package

    Work packages at Level 3 of the WBS are the lowest level where cost and schedule are assigned and tracked.

  7. A subcontractor's work depends on the general contractor supplying temporary power. This is best documented as:

    Answer: A constraint or assumption in the schedule

    Owner- or GC-furnished items that a subcontractor depends on must be documented as constraints or assumptions so accountability is clear.