CPT Production Planning & Scheduling Flashcards

6 cards from real CPT practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 6 CPT Production Planning & Scheduling flashcards as text
  1. What is a 'bottleneck' in a production process?

    Answer: The operation that limits overall throughput

    A bottleneck is the slowest operation in a process; it constrains the output rate of the entire production line.

  2. Which term describes the planned quantity of product to be produced in a specific time period?

    Answer: Production quota

    A production quota is the target output quantity assigned for a given shift, day, or week.

  3. Takt time is calculated by dividing:

    Answer: Available production time by customer demand rate

    Takt time = available production time ÷ customer demand; it sets the pace at which products must be completed.

  4. Which document communicates the quantity of a product to be built and its due date to the shop floor?

    Answer: Work order / job ticket

    A work order (job ticket) authorizes production of a specific quantity by a specific date and travels with the job on the floor.

  5. What is 'lead time' in a manufacturing environment?

    Answer: The total time from order release to completion of a part or product

    Lead time is the total elapsed time required to produce an item, from the release of a work order to delivery of the finished product.

  6. Forward scheduling is best suited for situations where:

    Answer: Material is available immediately and the earliest completion date is needed

    Forward scheduling starts from the current date and schedules operations forward to find the earliest possible completion date.