CSPM Time, Cost & Resource Management Flashcards
7 cards from real CPSM practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 CSPM Time, Cost & Resource Management flashcards as text
A project's Cost Variance (CV) is -$20,000 and its Earned Value (EV) is $80,000. What is the Actual Cost (AC)?
Answer: $100,000
CV = EV – AC, so AC = EV – CV = $80,000 – (–$20,000) = $100,000.
What scheduling technique splits a task and allows another higher-priority task to use the resource temporarily?
Answer: Preemptive scheduling
Preemptive scheduling interrupts a lower-priority task so a higher-priority task can use the shared resource.
Which document formally authorizes a project and provides the project manager with authority to apply organizational resources?
Answer: Project charter
The project charter formally authorizes the project and grants the project manager authority to allocate resources.
A schedule compression technique that overlaps phases or tasks that would normally be done sequentially is called:
Answer: Fast tracking
Fast tracking overlaps sequential activities to shorten the project schedule, often increasing risk.
In the critical chain method, what is a 'project buffer' used for?
Answer: Protecting the project end date from accumulated uncertainties
A project buffer in the critical chain method absorbs uncertainty from all tasks on the critical chain to protect the final project due date.
When should a project manager use analogous cost estimating?
Answer: Early in the project when limited information is available
Analogous estimating uses data from similar past projects and is most useful early on when detailed information is scarce.
A project is 50% complete with a BAC of $200,000, EV of $80,000, and AC of $100,000. What is the CPI?
Answer: 0.80
CPI = EV / AC = $80,000 / $100,000 = 0.80, meaning the project is getting only 80 cents of value for every dollar spent.