A process shows a Cpk of 0.85. What does this indicate?
Answer: The process is not capable of meeting specifications
A Cpk below 1.0 indicates the process is not capable of consistently producing output within specification limits.
Which document formally authorizes a quality audit and defines its scope?
Answer: Audit charter
An audit charter formally authorizes the audit function and defines its purpose, authority, and scope.
What is the primary purpose of a control chart's upper and lower control limits (UCL/LCL)?
Answer: Detect when a process is out of statistical control
Control limits are statistically derived boundaries used to distinguish common cause variation from special cause variation.
A company receives a major customer complaint about a recurring defect. The FIRST step in the 8D problem-solving process is to:
Answer: Form a cross-functional team
8D Step 1 (D1) requires forming a cross-functional team with the knowledge and authority to solve the problem.
ISO 9001:2015 uses a 'risk-based thinking' approach. Which clause most directly addresses this?
Answer: Clause 6 – Planning
Clause 6 of ISO 9001:2015 requires organizations to address risks and opportunities as part of quality management system planning.
Which sampling method selects every nth item from a production run?
Answer: Systematic sampling
Systematic sampling selects items at fixed intervals (every nth item), making it practical for continuous production processes.
When a gauge R&R study results in measurement variation exceeding 30% of total variation, the appropriate action is to:
Answer: Investigate and improve the measurement system
Measurement system variation above 30% is generally unacceptable and requires investigation and improvement of the gauge or measurement process.