Project Scope & Requirements Management Flashcards

7 cards from real CPP practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Project Scope & Requirements Management flashcards as text
  1. A project team discovers that a stakeholder's verbal request was implemented without a formal change request. This is an example of:

    Answer: Scope creep

    Scope creep refers to uncontrolled changes or continuous growth in a project's scope without proper authorization or change control.

  2. Which document formally defines what is and what is NOT included in the project?

    Answer: Project scope statement

    The project scope statement explicitly documents project deliverables and the work required to create them, including exclusions.

  3. A Requirements Traceability Matrix (RTM) primarily helps project teams:

    Answer: Track requirements from origin through delivery

    The RTM links requirements to their origin and traces them throughout the project life cycle, ensuring all requirements are addressed.

  4. When using a Work Breakdown Structure (WBS), the 100% rule means:

    Answer: The WBS captures 100% of the work defined in the scope statement

    The 100% rule states that the WBS includes 100% of the work defined by project scope and captures all deliverables including project management.

  5. A project manager notices stakeholders keep requesting small additions during sprints. The BEST preventive action is:

    Answer: Implement a formal change control process and enforce it consistently

    Implementing and enforcing a formal change control process ensures all scope additions are properly evaluated, approved, and resourced.

  6. In scope management, 'product scope' refers to:

    Answer: Features and functions characterizing the product or service

    Product scope describes the features and functions that characterize a product, service, or result, while project scope is the work to deliver it.

  7. Which technique is MOST effective for decomposing deliverables into smaller, more manageable components?

    Answer: Decomposition

    Decomposition is the technique used in Create WBS to subdivide project deliverables and work into smaller, more manageable components.