Project Governance & Portfolio Management Flashcards
7 cards from real CPP practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Project Governance & Portfolio Management flashcards as text
A portfolio manager notices that several projects are competing for the same scarce engineering resources. What is the most appropriate first step?
Answer: Conduct a portfolio-level resource capacity analysis
A portfolio-level resource capacity analysis identifies where demand exceeds supply and enables informed prioritization decisions.
Which governance document formally authorizes a project and establishes the project manager's authority?
Answer: Project Charter
The Project Charter is the governance document that formally authorizes the project and grants the project manager authority to apply resources.
In portfolio management, a 'strategic bucket' is best described as:
Answer: An allocated portion of investment capacity dedicated to a specific strategic theme
Strategic buckets are portions of the investment pool pre-allocated to specific strategic categories, ensuring balanced investment across themes.
A project steering committee is primarily responsible for:
Answer: Providing strategic direction, resolving escalated issues, and approving major changes
A steering committee governs at the strategic level—setting direction, unblocking escalations, and approving significant changes.
The primary purpose of a portfolio review meeting is to:
Answer: Assess portfolio health and make investment reallocation decisions aligned to strategy
Portfolio reviews assess overall health, strategic alignment, and whether to continue, adjust, or terminate investments.
When a project's benefits realization is measured after project closure, who typically owns this process?
Answer: The project sponsor or business owner
Benefits realization post-closure is owned by the sponsor or business owner because operational accountability transfers to them after project completion.
Which metric best indicates the strategic alignment of a project portfolio?
Answer: Percentage of portfolio investment mapped to strategic objectives
The proportion of investment tied to strategic objectives directly measures how well the portfolio advances organizational strategy.