Budgeting & Resource Management Flashcards
9 cards from real CPP practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 9 Budgeting & Resource Management flashcards as text
What is the primary goal of project budgeting?
Answer: To allocate and manage financial resources
The primary goal of project budgeting is to systematically plan, estimate, and control the financial resources required to complete the project successfully. It ensures that funds are allocated appropriately, costs are managed effectively, and the project stays within its financial constraints.
Which document outlines the estimated cost of a project?
Answer: Cost baseline
The cost baseline is the approved version of the project budget, typically presented as a time-phased budget. It serves as a benchmark against which actual project costs are compared to measure and monitor cost performance throughout the project lifecycle, indicating if the project is on track financially.
What is resource leveling used for?
Answer: To resolve resource conflicts and overallocation
Resource leveling is a technique specifically employed to address situations where resources are over-allocated or when there are conflicts in resource availability. By adjusting the schedule, it aims to smooth out resource usage, ensuring that no resource is assigned more work than they can handle at any given time.
Which technique estimates project costs based on historical data?
Answer: Analogous estimating
Analogous estimating is a top-down cost estimation technique that uses the actual cost or duration of a previous, similar project as the basis for estimating the current project. It is often used early in the project when detailed information is scarce, relying on historical data and expert judgment.
What does a resource histogram show?
Answer: Resource usage over time
A resource histogram is a bar chart that visually displays the amount of time a resource is scheduled to work on a project over a specific period. It helps project managers identify periods of high and low resource demand, aiding in resource leveling and allocation decisions to prevent over-utilization or idle time.
Why is cost control important in project management?
Answer: To maintain financial discipline and avoid overruns
Cost control is critical in project management to monitor project expenditures, identify variances from the budget, and take corrective actions. Its importance lies in maintaining financial discipline, preventing budget overruns, and ensuring the project delivers value within its approved financial limits.
Which cost estimating technique breaks down each activity?
Answer: Bottom-up estimating
Bottom-up estimating is a detailed cost estimation technique where the cost of individual work packages or activities is estimated first. These detailed estimates are then aggregated to arrive at the total project cost, providing a more accurate and precise budget by building from the ground up.
What is a key benefit of using a resource management plan?
Answer: Aligns resource needs with project goals
A resource management plan is crucial because it defines how project resources will be acquired, managed, and released. Its key benefit is ensuring that the right resources (people, equipment, materials) are available at the right time and are effectively utilized to achieve project objectives and goals.
How can Earned Value Management (EVM) assist in budgeting?
Answer: Monitors budget against project progress
Earned Value Management (EVM) is a project management methodology that integrates scope, schedule, and cost performance into a single system. It assists in budgeting by providing objective measures of project performance, allowing managers to track how much work has been completed for the money spent and forecast future costs.