A project has a Budget at Completion (BAC) of $200,000 and is 40% complete at the scheduled midpoint. The actual cost so far is $95,000. What is the Cost Performance Index (CPI)?
Answer: 0.84
EV = 40% × $200,000 = $80,000; CPI = EV/AC = $80,000/$95,000 ≈ 0.84.
Which EVM metric specifically measures how efficiently the project team is using the time allocated?
Answer: SPI
Schedule Performance Index (SPI) = EV/PV and measures schedule efficiency.
A project's Estimate at Completion (EAC) calculated as BAC/CPI is best used when:
Answer: Past cost performance is expected to continue
EAC = BAC/CPI assumes the current CPI will persist for all remaining work.
If a project's SPI is 0.90 and its CPI is 1.10, which statement best describes the project status?
Answer: Behind schedule but under budget
SPI 1 indicates under budget (cost efficient).
The Variance at Completion (VAC) formula is:
Answer: BAC − EAC
VAC = BAC − EAC; a negative VAC indicates a projected cost overrun.
Which term describes the authorized budget assigned to scheduled work?
Answer: Planned Value (PV)
Planned Value (PV), also called BCWS, is the authorized budget for work scheduled by a given date.
A project manager recalculates EAC as AC + (BAC − EV). This formula assumes:
Answer: The remaining work will be completed at budgeted rates
EAC = AC + (BAC − EV) assumes the remaining work proceeds exactly as originally planned.