CPP Performance Measurement & Reporting Flashcards
6 cards from real CPP practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 6 CPP Performance Measurement & Reporting flashcards as text
A Key Performance Indicator (KPI) is best described as:
Answer: A measurable value that tracks progress toward a strategic or project objective
KPIs are quantifiable metrics used to evaluate how effectively a project or organization is achieving its objectives.
What is the primary purpose of a project status report?
Answer: To communicate current project health, progress, and issues to stakeholders
A status report keeps stakeholders informed about where the project stands against baselines and highlights any issues requiring attention.
Which baseline is used to measure schedule performance in a project?
Answer: Schedule baseline
The schedule baseline is the approved version of the project schedule against which actual progress is compared.
A dashboard in project reporting is most useful because it:
Answer: Provides a quick visual summary of key metrics for rapid decision-making
Dashboards aggregate critical KPIs into an at-a-glance visual format that enables fast interpretation and informed decisions.
When actual cost exceeds planned cost at a reporting period, what is the financial implication?
Answer: The project is over budget for that period
Actual cost exceeding planned cost produces a negative cost variance, indicating the project is spending more than planned.
Which report would a project manager use to show trends in performance metrics over multiple reporting periods?
Answer: Trend report
A trend report plots metric data over time to reveal whether project performance is improving, deteriorating, or stable.