CPP Construction & Building Permits Flashcards
6 cards from real CPP practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 6 CPP Construction & Building Permits flashcards as text
What is a 'stop work order' and under what circumstances may it be issued?
Answer: An order halting construction when work is being done without a permit or in violation of code
Building officials can issue stop work orders when construction is occurring without a required permit, deviating from approved plans, or creating an unsafe condition, halting all work until violations are resolved.
What is the purpose of a 'geotechnical report' in the building permit process?
Answer: To characterize soil conditions and provide foundation design recommendations
Geotechnical reports analyze soil bearing capacity, groundwater depth, and subsurface conditions to provide engineers with data needed for safe foundation design.
What does the 'International Energy Conservation Code' (IECC) regulate in new construction?
Answer: Minimum energy efficiency standards for building envelopes and mechanical systems
The IECC sets minimum requirements for insulation, windows, HVAC efficiency, and lighting to reduce energy consumption in new and renovated buildings.
What is a 'demolition permit' and what environmental review may accompany it?
Answer: A permit required to demolish a structure, often with asbestos and lead surveys required
Demolition permits authorize the teardown of structures and typically require hazardous materials surveys for asbestos and lead paint before work begins to protect worker and public health.
What is the significance of 'fire-resistive construction' classifications under the IBC?
Answer: They determine how long building elements must resist fire before failure, affecting height and area limits
IBC construction types (Type I through V) specify fire-resistance ratings for structural elements, which in turn determine maximum allowable building heights and floor areas without sprinklers.
What triggers a 'change of occupancy' permit requirement when renovating an existing building?
Answer: Changing the use of a building to a different occupancy classification under the IBC
When a building changes from one IBC occupancy group to another (e.g., industrial to residential), a change of occupancy review is required to ensure the building meets code requirements for the new use.