What is the difference between a 'prescriptive' and 'performance-based' building code approach?
Answer: Prescriptive specifies exact methods; performance-based allows any method that achieves the required outcome
Prescriptive codes specify exact materials and methods, while performance-based codes define outcomes (e.g., fire resistance rating) and allow designers to use any method to achieve them.
What is a 'grading permit' and when is it typically required?
Answer: A permit required for earthwork, excavation, or fill activities that disturb a specified area or volume of soil
Grading permits are required for significant earthwork to ensure proper drainage, erosion control, and slope stability, and to prevent impacts on neighboring properties and waterways.
Under the Americans with Disabilities Act (ADA), when must an existing building be brought into compliance during renovation?
Answer: When the renovation affects the path of travel to the primary function area, up to 20% of renovation cost
ADA regulations require that alterations to primary function areas trigger accessibility improvements to the path of travel, restrooms, and drinking fountains serving that area, up to 20% of the alteration cost.
What is a 'right-of-way' (ROW) permit in construction?
Answer: A permit required to perform work within a public street, sidewalk, or utility easement
ROW permits allow contractors to occupy or disturb public rights-of-way for activities like utility installation, driveway connections, or lane closures, with conditions to maintain public safety.
What is the International Residential Code (IRC) primarily designed for?
Answer: One- and two-family dwellings and townhouses not more than three stories
The IRC covers detached one- and two-family dwellings and townhouses not exceeding three stories, providing a standalone code that addresses structural, electrical, plumbing, and mechanical systems.
What is 'plan review' in the building permit process?
Answer: The technical examination of construction drawings and specifications for code compliance before permit issuance
Plan review is conducted by building department staff or third-party reviewers who examine permit drawings for compliance with building, fire, zoning, and other applicable codes before permits are issued.