Project Planning & Execution Flashcards
7 cards from real CPP practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 7 Project Planning & Execution flashcards as text
Which scheduling technique shows task dependencies and the longest path through a project?
Answer: Critical Path Method (CPM)
CPM identifies the sequence of tasks with zero float, determining the minimum project duration.
A packaging project scope creep occurs when:
Answer: Unapproved features or work are added beyond the original scope
Scope creep refers to uncontrolled expansion of project scope without adjustments to time, cost, or resources.
In packaging project management, a 'gate review' is best described as:
Answer: A formal decision point to approve continuation to the next phase
Gate reviews are structured checkpoints where stakeholders evaluate progress before authorizing the next project phase.
When creating a packaging project budget, which cost category covers equipment wear and aging over the project lifetime?
Answer: Depreciation
Depreciation accounts for the reduction in asset value over time and is included in capital cost planning.
A packaging development team is behind schedule. The project manager decides to assign additional resources to critical tasks. This technique is called:
Answer: Crashing
Crashing adds resources to shorten the duration of critical path activities, typically increasing cost.
Which document formally authorizes a packaging project and identifies the project manager?
Answer: Project charter
The project charter is the foundational document that officially initiates a project and grants authority to the project manager.
What is the primary purpose of a risk register in a packaging project?
Answer: To track identified risks, their probability, impact, and response plans
A risk register is a centralized log that captures all identified risks along with assessment data and planned responses.