  1. Which scheduling technique shows task dependencies and the longest path through a project?

    Answer: Critical Path Method (CPM)

    CPM identifies the sequence of tasks with zero float, determining the minimum project duration.

  2. A packaging project scope creep occurs when:

    Answer: Unapproved features or work are added beyond the original scope

    Scope creep refers to uncontrolled expansion of project scope without adjustments to time, cost, or resources.

  3. In packaging project management, a 'gate review' is best described as:

    Answer: A formal decision point to approve continuation to the next phase

    Gate reviews are structured checkpoints where stakeholders evaluate progress before authorizing the next project phase.

  4. When creating a packaging project budget, which cost category covers equipment wear and aging over the project lifetime?

    Answer: Depreciation

    Depreciation accounts for the reduction in asset value over time and is included in capital cost planning.

  5. A packaging development team is behind schedule. The project manager decides to assign additional resources to critical tasks. This technique is called:

    Answer: Crashing

    Crashing adds resources to shorten the duration of critical path activities, typically increasing cost.

  6. Which document formally authorizes a packaging project and identifies the project manager?

    Answer: Project charter

    The project charter is the foundational document that officially initiates a project and grants authority to the project manager.

  7. What is the primary purpose of a risk register in a packaging project?

    Answer: To track identified risks, their probability, impact, and response plans

    A risk register is a centralized log that captures all identified risks along with assessment data and planned responses.