(CPIM) Certified in Planning and Inventory Management Practice Test
CPIM CPIM Master Planning and MRP Questions and Answers
What is the primary input to the Material Requirements Planning (MRP) process?
Select your answer
A
The Master Production Schedule (MPS)
B
The inventory status record only
C
The sales forecast only
D
The bill of materials only
Hint