What is 'input/output control' (I/O control) used for in production activity control?
Select your answer
A
To monitor and manage the flow of work into and out of a work center to control queue length and lead times
B
To track the number of defects entering and leaving a process
C
To balance machine utilization across shifts
D
To reconcile planned versus actual MRP orders
Hint