โ† All CPIM Flashcard Decks

CPIM Capacity Planning and Management Questions and Answers Flashcards

6 cards from real CPIM practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 6 CPIM Capacity Planning and Management Questions and Answers flashcards as text
  1. What is 'input/output control' (I/O control) used for in production activity control?

    Answer: To monitor and manage the flow of work into and out of a work center to control queue length and lead times

    I/O control compares planned versus actual input and output at a work center, allowing planners to manage backlog and control actual lead times.

  2. What is a 'load profile' in capacity planning?

    Answer: A display of capacity requirements for a work center over time, showing planned load versus available capacity

    A load profile visually shows whether a work center is overloaded or underloaded across future planning periods, enabling proactive capacity adjustments.

  3. When a work center is consistently overloaded in CRP, which of the following is NOT a valid resolution strategy?

    Answer: Increasing safety stock levels for finished goods

    Increasing safety stock does not add productive capacity; valid overload solutions include overtime, alternate routings, order rescheduling, or subcontracting.

  4. What is the 'theory of constraints' (TOC) concept of a 'bottleneck' resource?

    Answer: A resource whose capacity is equal to or less than the demand placed on it, limiting system throughput

    According to TOC, a bottleneck is the one resource that constrains the entire system's output, so improving it directly improves overall throughput.

  5. In the Theory of Constraints, what does 'drum-buffer-rope' (DBR) refer to?

    Answer: A scheduling method where the bottleneck (drum) sets the pace, a buffer protects it, and a rope synchronizes upstream release

    DBR uses the bottleneck's schedule as the production drum, places a time buffer before it for protection, and ties upstream work release to the constraint's pace.

  6. What is 'capacity cushion' and why might a company maintain it?

    Answer: Extra capacity above expected demand, maintained to handle demand surges and protect service levels

    A capacity cushion provides a buffer against demand uncertainty, machine breakdowns, and quality problems, helping companies maintain customer service levels.