CPIM - Certified in Planning and Inventory Management Detailed Scheduling Questions and Answers
A work center's planned input is 100 standard hours, and the planned output is 100 standard hours. Over the past week, the actual input was 90 hours, and the actual output was 80 hours. What is the immediate conclusion a production planner should draw using input/output control?