CPE Project Management & Engineering Economics Flashcards

6 cards from real CPE practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 6 CPE Project Management & Engineering Economics flashcards as text
  1. What does the term 'net present value' (NPV) mean in engineering economics?

    Answer: The current worth of all future cash flows discounted at a required rate of return

    NPV discounts all future project cash flows to the present using a required rate of return; a positive NPV indicates the project adds value.

  2. In a capital project, what is a 'Work Breakdown Structure' (WBS)?

    Answer: A hierarchical decomposition of the project scope into manageable deliverables and work packages

    A WBS divides total project scope into smaller, controllable components to facilitate planning, cost estimating, and progress tracking.

  3. What is the 'critical path' in project scheduling?

    Answer: The longest sequence of dependent tasks that determines the minimum project duration

    The critical path is the longest chain of dependent activities; any delay on the critical path directly extends the overall project finish date.

  4. Which contract type places the greatest financial risk on the contractor?

    Answer: Lump-sum (fixed-price) contract

    In a lump-sum contract the contractor agrees to complete the scope for a fixed price, bearing the risk of cost overruns if actual costs exceed the bid.

  5. What is 'straight-line depreciation' for a capital asset?

    Answer: Distributing the asset's cost evenly over its useful life in equal annual amounts

    Straight-line depreciation divides the depreciable cost (purchase price minus salvage value) equally across each year of the asset's expected useful life.

  6. A Gantt chart is primarily used in project management to:

    Answer: Visualize the project schedule by showing task durations and timelines in bar format

    A Gantt chart displays project activities as horizontal bars on a timeline, making it easy to see task durations, sequences, and overall schedule.