โ† All CPE Flashcard Decks

Engineering Economics & Contract Management Flashcards

7 cards from real CPE practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Engineering Economics & Contract Management flashcards as text
  1. A project has a Benefit-Cost Ratio (BCR) of 0.85. What does this indicate?

    Answer: The project returns $0.85 for every $1 invested

    A BCR less than 1.0 means the present value of benefits is less than costs, indicating the project is not economically justified.

  2. Under a Cost-Plus-Incentive-Fee (CPIF) contract, the fee increases when:

    Answer: The contractor underruns the target cost

    In a CPIF contract, the contractor earns a higher fee when actual costs fall below the target cost, sharing the savings with the owner.

  3. What is the Modified Internal Rate of Return (MIRR) designed to address?

    Answer: Multiple sign changes in cash flows causing multiple IRR values

    MIRR resolves the problem of multiple IRR values that arise when a project's cash flow stream changes sign more than once.

  4. In contract law, 'liquidated damages' clauses must be:

    Answer: A genuine pre-estimate of loss, not a penalty

    Liquidated damages must represent a reasonable estimate of the owner's actual loss at the time of contract formation to be enforceable.

  5. A machine costs $50,000 and has a salvage value of $5,000 after 9 years. Using straight-line depreciation, the annual depreciation charge is:

    Answer: $5,000

    Annual depreciation = ($50,000 - $5,000) / 9 = $45,000 / 9 = $5,000 per year.

  6. Which contract type places the MOST financial risk on the owner?

    Answer: Cost-plus-percentage-of-cost

    Cost-plus-percentage-of-cost contracts give the contractor no incentive to control costs since their fee grows as costs increase, maximizing owner risk.

  7. The capitalized cost of a project with an annual operating cost of $20,000 and an interest rate of 5% is:

    Answer: $400,000

    Capitalized cost for a perpetual series = Annual Cost / Interest Rate = $20,000 / 0.05 = $400,000.